Government inaugurates Manduriac hydroelectric of $ 183 million

President Rafael Correa inaugurated on March 19 the Manduriacu hydroelectric power station, one of eight which plans to build with loans from China, Russia and Brazil. Located between the provinces of Pichincha and Imbabura, the project, whose investment is $ 183 million, will...

Construction company of Toachi-Pilatón project has been fined since 2013 for $ 3.25 million

China International Water & Electric (CWE), construction company of the hydroelectric project Toachi-Pilatón, has been fined for more than $ 3.25 million due to defaults on its contract in terms of time, technical procedures, and standards of health and safety. The sanctions...

Toachi-Pilatón has an advance of 62% in one year of delay

Even though the Toachi-Pilatón hydroelectric project, located two hours from Quito, has a steadily progress in its works, it has a near one-year delay. The works are performed in 10 different fronts between km 59 and 76 of the Alóag-Santo Domingo route. The project has an advance...

Hydroelectric project works continues

The Coca – Codo Sinclair opens in 2016, despite the problems that have been reported during the construction process. Thus said the Vice-President of the Republic, Jorge Glas, after being consulted on the subject. With an advance of a 64%, the main problem of the...