• ENGLISH
  • ESPAÑOL
facebook
twitter
  • National>Entertainment
  • National>Local Economics
  • National>Local Politics
  • National>Society
  • National>Sports
BREAKING NEWS
Cristian Espinosa was appointed Ambassador of Ecuador to the United States
Daniel Noboa receives the credentials of the new United States ambassador
40,000 women will receive scholarships in higher education
Julian Assange released from prison, after agreement with the United States
Armed Forces: Criminal gangs have lost USD 1.2 billion due to military operations in Ecuador
Minister of Defense: “It is not fair that some risk their lives, while others play with justice”
How can green banana flour enhance baked goods?
“I’m crazy for wanting to serve my country,” says Daniel Noboa at the presentation of “La Cárcel del Encuentro” in Santa Elena
Construction of the Encuentro maximum-security prison in Santa Elena begins
National blackout in Ecuador due to transmission line failure, confirms the Government

Repair of the Bajo Alto gas plant will cost $ 19.2 million

Posted On 14 Jan 2019

Ecuadornews:

Some $ 19.2 million will have to be invested in the Bajo Alto natural gas liquefaction plant to operate under international efficiency and safety standards. Thus, the work that initially had to cost $ 36 million and ended in $ 76 million would reach almost $ 95.2 million.

The plant, built in El Oro by Ros Roca Indox, was audited by international companies endorsed by the United Nations Development Program (UNDP). It presents, among its main and most expensive problems, subsidence and a deficient supply of energy for the plant.

The subsidence occurred, according to the report, due to incomplete design and poor construction. Is that, according to the study conducted by the Spanish company Tecnatom, there was no preparation of the land or a geotechnical report.

There would also be signs of poor execution of fillings and foundations.

The foundation works would cost $ 6.9 million; the report states that “the perimeter of the slabs must be rebuilt by installing piles approximately 80 cm in diameter, joined by a mooring head beam between them, and interspersed with gravel columns”. He also advises “in some areas, to demolish and reconstruct the slab on which the main elements are located”.

As for the power supply of the plant, a “serious error” had been committed. Being a gas plant, diesel engines were purchased for power generation. Then they were tried to adapt to gas.

The auditor recommends buying gas engines that could cost $ 8.9 million. Despite having a very close source of electricity, that is, the Termomachala power plant, the same international company recommends that the plant does not depend on the National Interconnected System, as it claims that it is not reliable.

The report also indicates that after the series of remediations that should be done to the plant, it could have to stop for 150 days.

Esta imagen tiene un atributo ALT vacío; su nombre de archivo es artebajoalto.jpg

Although it is currently operating at 50%, the question that arises is what will happen to the gas from the Amistad field that reached Bajo Alto.

According to the figures of Petroamazonas, which manages the offshore gas field, this year Termomachala will require 63 million cubic feet per day of natural gas; Low High, 12 million feet; and Gasvesubio (a plant of the Eljuri Group, up against Bajo Alto), 14 million.

Petroamazonas explained that if the plant comes to a halt, the production that was consumed by Bajo Alto would pass directly, through its dehydrating plant, to Termomachala, so there would be no waste.

He explained that currently natural gas cannot be stored, so it must be consumed online, at the same time it is produced.

However, according to industry sources, Termomachala’s demand for natural gas is well below the figures that Petroamazonas would expect.

The role played by Gasvesubio in the new circumstances is still unknown. A few months ago, the Ministry of Energy and Non-Renewable Natural Resources asked the Comptroller’s Office to examine the contract signed with Petroecuador for the provision of 14 million cubic feet.

License

According to the report of the Spanish Tecnatom, at the beginning of the construction of the plant (November 2009) they did not have the environmental license (issued in November 2010), which implies that the environmental construction aspects were not met in the main construction contract nor the monitoring plans during the execution of the work. (I)

Source: https://www.eluniverso.com/noticias/2019/01/14/nota/7137899/reparar-planta-bajo-alto-costara-192-millones

About the Author
  • google-share
Previous Story

Amazon revives the case of the Ecuadorian Lorena Bobbit after 25 years

Next Story

Andrés Páez claims to have “evidence” of transfers from ODEBRECHT to Glory International, which would link to Jorge Glas

SEARCH

LATEST NEWS

ecuadortimes-cristian-espinosa-was-appointed-ambassador-of-ecuador-to-the-united-states_cristian-espinosa-fue-nombrado-embajador-de-ecuador-en-estados-unidos

Cristian Espinosa was appointed Ambassador of Ecuador to the United States

Posted On 28 Jun 2024
ecuadortimes-daniel-noboa-receives-the-credentials-of-the-new-united-states-ambassador_daniel-noboa-recibe-las-cartas-credenciales-del-nuevo-embajador-de-estados-unidos

Daniel Noboa receives the credentials of the new United States ambassador

Posted On 27 Jun 2024
40-000-mujeres-recibiran-becas-en-educacion-superior

40,000 women will receive scholarships in higher education

Posted On 26 Jun 2024
Copyright © 2010 - 2019. All Rights Reserved. EcuadorTimes.net